Road Construction Projects

The following Town of Edgewood Road construction projects may impact traffic and road access. Be advised Traffic Fines Double in construction zones. 

CURRENT ROAD PROJECTS

East Venus during construction

Nugent Road - 1 mile

Dates: Prep work Mid-November 2025 - Spring 2026; Paving in Summer 2026

DETOUR Hours: Intermittent traffic control and closures, as needed 

Alternative Route: Use NM 344 to Frost Road -or- Hill Ranch Rd to Horton Rd north to Nugent Rd west to Broken Arrow north to Frost Rd. 

Purpose: Construction: grading and installation of culverts, then paving (Final Phase of project)

COMPLETED TOWN ROAD PROJECTS

road paving roller

The Town has paved 4 miles of roads between Oct. 2023 - Feb. 2026. This includes planning, water diversion/drainage/culvert installation, build-up of roadway as needed, materials, and chipseal paving. For details on completed projects, see: Roads - Past Projects.

NMDOT ROAD PROJECTS IN EDGEWOOD

NM 344 after NMDOT paving

 

NM 344 (NMDOT project - completed Dec. 2025)

Dates: December 2025 - road striping completed

Dates: Aug - October 2025 - (impacted by temporary federal shut down)

 

Route 66 (NMDOT project - completed between Edgewood and Moriarty)

Dates: December 2025 - road striping completed

Dates: Aug 6 - October 2025 - (striping delayed due to federal shut down)